Japan has just over 250 MW of offshore wind installed but targets 10 GW by 2030, 30–45 GW by 2040, and over 65% local content across the supply chain by 2040. Most of its potential lies in floating wind, and rising costs have already pushed Mitsubishi out of its first-round projects. This Cover Note sets out where Japan's offshore wind sector stands and the narrow channels through which Chinese suppliers could realistically contribute.

Japan has a vast sea space with good wind resources, but its seabed falls away steeply from the coast. Fixed-bottom potential is only around 70 GW, against more than 1,000 GW for floating wind. Rising LNG prices in 2026 have again raised energy security concerns and wholesale electricity prices.
Key takeaways:
Projects are getting much bigger, and much harder. Three auction rounds have awarded just over 4 GW to projects of 300–900 MW. Mitsubishi Corporation pulled out of all three Round 1 projects, citing higher supply chain costs and revenue uncertainty. If Rounds 2 and 3 are not built, the targets are highly unlikely to be met.
The government is stepping in. Reforms include access to the 20-year fixed-price LTDA scheme, easier switching of turbine suppliers and port development. From April 2026, permitting has been extended into the EEZ, opening up a huge area for floating projects.
Japan is building a domestic supply chain. Partnerships such as Toshiba's planned assembly of GE Haliade-X nacelles and a Vestas–Nippon Steel tower steel agreement draw on Japan's strengths in specialty steel, shipbuilding and high-voltage transmission.
Screening of Chinese investment is strict. No Chinese investments have been recorded. Foreign stakes in projects above 1% are tightly regulated, and foreign SOEs are effectively excluded.
Three channels are most promising: equipment supply (subject to certification and economic-security disclosure), investment in manufacturing for foundations, towers and selected components, and licensing turbine technology to Japanese manufacturers, which falls outside investment screening entirely.